What does it do?
- This explains the Fourteenth Amendment to the Public Procurement Regulations, 2064, published on 15 Baisakh 2082 with immediate commencement. Later amendments exist: this is not the current consolidated text or a statement that its application periods remain open. The catalogue’s unconfirmed legal status is unchanged.यो तत्काल प्रारम्भ हुने गरी २०८२ साल वैशाख १५ गते प्रकाशित सार्वजनिक खरिद नियमावली, २०६४ को चौधौँ संशोधनको व्याख्या हो। पछिल्ला संशोधन पनि छन्; यो हालको एकीकृत पाठ वा यसका आवेदन अवधि अझै खुला छन् भन्ने दाबी होइन। सूचीको पुष्टि नभएको कानूनी स्थिति अपरिवर्तित छ। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Preamble and amendment Rule 1, pp.1-2
- Design-build assigns design and construction to the same contractor. EPC covers engineering including design, procurement and construction, with operation and maintenance for a specified period where needed. Before either procurement begins, the public body must study economic, social, technical and environmental feasibility and prepare a report and conceptual design. The report may provide a preliminary basis, stated in bidding documents; the amended schedules describe suitable project categories rather than requiring these methods for every project.डिजाइन र निर्माण सम्झौतामा एउटै निर्माण व्यवसायीले डिजाइन र निर्माण गर्छ। ई.पी.सी.मा डिजाइनसहित इन्जिनियरिङ, खरिद र निर्माण तथा आवश्यकताअनुसार तोकिएको अवधिको सञ्चालन र मर्मत सम्भार पर्छन्। यी प्रक्रियाबाट खरिद सुरु गर्नुअघि सार्वजनिक निकायले आर्थिक, सामाजिक, प्राविधिक र वातावरणीय सम्भाव्यता अध्ययन गरी प्रतिवेदन र प्रारूप डिजाइन तयार गर्नुपर्छ। प्रतिवेदनलाई प्रारम्भिक आधार लिन सकिन्छ र सो कुरा बोलपत्र कागजातमा उल्लेख गर्नुपर्छ; संशोधित अनुसूचीले उपयुक्त आयोजनाका प्रकार बताउँछन्, सबै आयोजनामा यी विधि अनिवार्य गर्दैनन्। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 2-3,23; base Rules 2(य)-(ल),3(1)(ट),3(2), Schedule 4; pp.2-3,20-22
- Design-build and EPC use separate cost-estimate templates. Both include 15% bidder overhead; design-build then includes staff, minor-cost and price/physical-contingency additions. EPC instead provides inflation adjustment for contracts exceeding two years and staff/minor-cost additions. The notes distinguish bid-comparison bases from other estimate totals; design-build contingencies must not simply be copied into EPC. Consulting-service estimates also use applicable norms prepared by the parent ministry or another Nepal Government ministry.डिजाइन र निर्माण तथा ई.पी.सी.का लागत अनुमान ढाँचा अलग छन्। दुवैमा बोलपत्रदाताको १५ प्रतिशत ओभरहेड पर्छ; डिजाइन र निर्माणमा त्यसपछि कर्मचारी, सानातिना खर्च तथा मूल्य र भौतिक कन्टिन्जेन्सीका रकम पर्छन्। ई.पी.सी.मा दुई वर्षभन्दा बढी अवधिको सम्झौताका लागि मुद्रास्फीति समायोजन र कर्मचारी तथा सानातिना खर्चका रकम छन्। टिप्पणीले बोलपत्र तुलना गर्ने आधार र अन्य अनुमान रकम छुट्याउँछ; डिजाइन र निर्माणका कन्टिन्जेन्सी ई.पी.सी.मा जस्ताको तस्तै सार्न मिल्दैन। परामर्श सेवाको लागत अनुमानमा तालुक मन्त्रालय वा नेपाल सरकारको अर्को मन्त्रालयले तयार गरेको लागू हुने नर्म्स पनि आधार हुन्छ। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 4,6,23; base Rules 10(8),12(2)(क), Schedules 1ख,1ग; pp.3-5,23-26
- Framework or unit-rate agreements have two stages and may last up to five years. National bidding gives at least thirty days at the first stage, selects qualified suppliers and concludes agreements without bid security for that agreement. The second stage may use a closed supplier list or allow other suppliers to compete for call-off contracts, with delivery conditions for fixed, indefinite or required quantities. This is not a blanket security exemption for subsequent contracts.संरचनात्मक वा एकाइ दर सम्झौता दुई चरणमा हुन्छ र पाँच वर्षसम्म गर्न सकिन्छ। राष्ट्रियस्तरको बोलपत्रमा पहिलो चरणमा कम्तीमा तीस दिन दिई योग्य आपूर्तिकर्ता छनोट र सम्झौता गरिन्छ; त्यस सम्झौताका लागि बोलपत्र जमानत चाहिँदैन। दोस्रो चरणमा बन्द सूची वा अन्य आपूर्तिकर्तालाई समेत प्रतिस्पर्धा गराई निश्चित, अनिश्चित वा आवश्यक परिमाण र आपूर्ति समयका शर्तसहित कल अफ सम्झौता गर्न सकिन्छ। यो पछिका सबै सम्झौतामा जमानत नचाहिने व्यवस्था होइन। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 7,23(2); base Rule 21क, Schedule 3(ख); pp.5-6,20
- Design-build and EPC contracts must specify at least five-year defect-correction periods, with EPC operation and maintenance periods also stated. This does not make every maintenance or operation period five years. EPC uses lump-sum competition. The changes also require relevant project, design, quality and output information. Contractors submit designs within the contractual period; the public body checks scope and standards before the tender-inviting office head gives the start instruction within thirty days of receipt.डिजाइन र निर्माण तथा ई.पी.सी. सम्झौतामा कम्तीमा पाँच वर्षको त्रुटि सच्याउने अवधि र ई.पी.सी.मा सञ्चालन तथा मर्मत सम्भारको अवधि पनि खुलाउनुपर्छ। यसले सबै मर्मत वा सञ्चालन अवधि पाँच वर्ष बनाउँदैन। ई.पी.सी.मा एकमुष्ट सम्झौताका आधारमा प्रतिस्पर्धा हुन्छ। परिवर्तनले सम्बन्धित आयोजना, डिजाइन, गुणस्तर र नतिजाको जानकारी पनि माग्छ। व्यवसायीले सम्झौताको अवधिभित्र डिजाइन पेस गर्छ; सार्वजनिक निकायले कार्यक्षेत्र र मापदण्ड जाँचेपछि बोलपत्र आह्वान गर्ने कार्यालय प्रमुखले प्राप्त भएको तीस दिनभित्र काम सुरु गर्ने जानकारी दिन्छ। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 8,12,17; base Rules 22,37(झ1),113क; pp.6-7,10,12-13
- The experience test considers comparable completed work within ten years and specified annual production capacity. The general test requires a contract worth at least 40% of the estimate for procurement from Rs 2 crore through Rs 10 crore, or 60% above that range. The EPC proviso instead requires similar design-build, EPC or turnkey experience worth at least 40%; for a joint venture one partner must meet that similar-work requirement and each partner needs public-construction experience worth at least 25%. Design-build/EPC bidders also document their project understanding, design method and implementation approach.अनुभव परीक्षणले दस वर्षभित्र पूरा गरेको समान प्रकृतिको काम र तोकिएको वार्षिक उत्पादन क्षमता हेर्छ। सामान्य व्यवस्थामा दुई करोडदेखि दस करोड रुपैयाँसम्मको खरिदका लागि लागत अनुमानको कम्तीमा ४० प्रतिशत र त्यसभन्दा बढीमा ६० प्रतिशत बराबरको सम्झौता चाहिन्छ। ई.पी.सी.को अलग व्यवस्थामा कम्तीमा ४० प्रतिशत बराबरको समान डिजाइन र निर्माण, ई.पी.सी. वा टर्न की अनुभव चाहिन्छ; संयुक्त उपक्रममा एक साझेदारले त्यो समान कामको शर्त र प्रत्येक साझेदारले कम्तीमा २५ प्रतिशत बराबरको सार्वजनिक निर्माण अनुभव पूरा गर्नुपर्छ। डिजाइन र निर्माण तथा ई.पी.सी. बोलपत्रदाताले आयोजना बुझाइ, डिजाइन विधि र कार्यान्वयन पद्धति पनि पेस गर्छन्। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rule 9; base Rule 26(1)(ग),(छ); pp.7-9
- Chemical-fertilizer estimates use international FOB price reports and specified freight, handling, transport, bank and insurance costs. Before the bid deadline the estimate is revised using the latest report, without requiring changes to the original evaluation bases or bid-security amount. Fertilizer financial proposals use the revised estimate; their opening requires at least seven days’ notice, and bid documents state validity through thirty days from technical-proposal opening. These timing and price rules are fertilizer-specific.रासायनिक मलको लागत अनुमानमा अन्तर्राष्ट्रिय एफ.ओ.बी. मूल्य प्रतिवेदन र तोकिएका भाडा, मालसामान व्यवस्थापन, ढुवानी, बैङ्क तथा बीमा खर्च आधार हुन्छन्। बोलपत्रको अन्तिम म्यादअघि पछिल्लो प्रतिवेदनअनुसार अनुमान संशोधन हुन्छ; यसले सुरुका मूल्याङ्कन आधार वा जमानत रकम बदल्नुपर्ने बनाउँदैन। मलका आर्थिक प्रस्ताव संशोधित अनुमानबाट मूल्याङ्कन हुन्छन्; खोल्न कम्तीमा सात दिनको सूचना चाहिन्छ र प्राविधिक प्रस्ताव खोलेदेखि तीस दिनसम्मको मान्य अवधि बोलपत्र कागजातमा खुलाउनुपर्छ। यी समय र मूल्यका नियम मलका लागि हुन्। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 5,11,13-14; base Rules 11(3)-(5),31ज(5),54 proviso,64(6); pp.4-5,10-11
- Design-build contractors bear specified design, geological, commercial, technical and other risks, except scrutiny-period claims concerning physical conditions unexpectedly changed by natural disaster. EPC assigns its design, construction and maintenance risks to the contractor without repeating that exception. Design-build variations may follow investigation of such disaster-related changes or public-body-required additions or modifications; EPC variations are prohibited except for additions or modifications required by the public body.डिजाइन र निर्माण व्यवसायीले तोकिएका डिजाइन, भौगर्भिक, व्यापारिक, प्राविधिक र अन्य जोखिम व्यहोर्छ; प्राकृतिक विपद्ले अप्रत्याशित रूपमा बदलेको भौतिक अवस्थाबारे स्क्रुटिनी अवधिमा गरिने दाबीको अपवाद छ। ई.पी.सी.ले डिजाइन, निर्माण र मर्मतका जोखिम व्यवसायीमा राख्छ र त्यही अपवाद दोहोर्याउँदैन। डिजाइन र निर्माणमा त्यस्तो विपद्जन्य परिवर्तन वा निकायले मागेको थपघट वा परिमार्जन जाँचेर भेरिएसन दिन सकिन्छ; ई.पी.सी.मा निकायले मागेको थपघट वा परिमार्जनबाहेक भेरिएसन निषेध छ। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 16,18; base Rules 111क,118(6)-(7); pp.11-13
- Replacement Rule 120क creates conditional extensions for unfinished contracts whose periods expired or could not be extended for listed causes, including government/body suspension, omitted budget, insufficient-budget payment delay or contractual compensation events. It allowed applications within thirty days of commencement with evidence, revised schedules and undertakings not to claim extra money because of extension. Officers check schedules and valid securities and insurance; the Rule 67 officer may extend the actual time needed. Decisions are due within thirty days of application, with departmental action for decision delay. No liquidated damages apply during the extended period.प्रतिस्थापित नियम १२०क ले सरकार वा निकायबाट काम रोकिएको, बजेट नछुट्याइएको, अपर्याप्त बजेटले भुक्तानी ढिलो भएको वा सम्झौताका क्षतिपूर्ति घटनाजस्ता तोकिएका कारणले अवधि सकिएका वा थप हुन नसकेका अधुरा सम्झौताका लागि शर्तसहित म्याद थप व्यवस्था गर्छ। प्रारम्भ भएको तीस दिनभित्र प्रमाण, संशोधित कार्यतालिका र म्याद थपका कारण अतिरिक्त रकम दाबी नगर्ने प्रतिबद्धतासहित आवेदन दिन सकिने व्यवस्था थियो। अधिकारीले कार्यतालिका र मान्य जमानत तथा बीमा जाँच्छन्; नियम ६७ को अधिकारीले वास्तवमा चाहिने अवधि थप गर्न सक्छ। आवेदनको तीस दिनभित्र निर्णय गर्नुपर्छ र निर्णय ढिलाइमा विभागीय कारबाही हुन्छ। थप अवधिमा पूर्वनिर्धारित क्षतिपूर्ति लाग्दैन। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rule 19; replaced base Rule 120क(1)-(5); pp.14-16
- Failure to apply on time or complete within the extension leads to termination, but a listed cause recurring permits a further application within thirty days after the extended period ends. Termination requires a written blacklisting referral, not automatic blacklisting. Rule 120क also provides ministry monitoring, counting from the extension decision with intervening time treated as extended, and possible milestone adjustment. These historical conditions do not establish an open application window now.समयमा आवेदन नदिए वा थप अवधिमा काम नसके सम्झौता अन्त्य हुन्छ; तर तोकिएको कारण फेरि परे थप अवधि सकिएको तीस दिनभित्र फेरि आवेदन दिन सकिने अपवाद छ। अन्त्य हुँदा कालोसूचीका लागि लिखित सिफारिस गर्नुपर्छ, स्वतः कालोसूचीमा पर्ने होइन। नियम १२०क मा मन्त्रालयको अनुगमन, निर्णयबाट अवधि गणना गर्दा बीचको समय पनि थप भएको मान्ने र माइलस्टोन समायोजन गर्न सकिने व्यवस्था छन्। यी ऐतिहासिक शर्तले अहिले आवेदन खुला रहेको प्रमाणित गर्दैनन्। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rule 19; replaced base Rule 120क(6)-(9); pp.16-17
- For design-build or EPC contracts, or other contracts whose defect-correction or maintenance period exceeds twelve months, the public body may on request after 60% work completion return up to 60% of deducted retention against a bank guarantee of 110% of the refund. If the contractor fails to correct defects or maintain within the period, the body may use retention or guarantee funds for that work. A separate Rule 110(4) proviso allows a separately lodged guarantee for the specified low-bid amount: its 50% calculation concerns the amount below the fifteen-percent threshold, not half the whole bid. That separate guarantee must remain valid at least one month beyond the contract completion period. Payment provisions also add design-build/EPC milestones, measurable results and progress bases.डिजाइन र निर्माण वा ई.पी.सी. सम्झौता, वा बाह्र महिनाभन्दा बढी त्रुटि सच्याउने वा मर्मत अवधि भएका अन्य सम्झौतामा ६० प्रतिशत काम पूरा भएपछि माग आए काटिएको धरौटीको बढीमा ६० प्रतिशत रकम फिर्ता रकमको ११० प्रतिशत बैङ्क जमानत लिएर निकायले फिर्ता गर्न सक्छ। व्यवसायीले अवधिभित्र त्रुटि नसच्याए वा मर्मत नगरे निकायले धरौटी वा जमानतबाट त्यो काम गर्न सक्छ। अलग नियम ११०(४) ले तोकिएको न्यून बोलपत्र रकमका लागि छुट्टै जमानत राख्न दिन्छ; यसको ५० प्रतिशत गणना पन्ध्र प्रतिशतको सीमाभन्दा तलको रकममा हुन्छ, पूरै बोलपत्रको आधामा होइन। त्यो छुट्टै जमानत सम्झौताको काम सम्पन्न गर्ने अवधिभन्दा कम्तीमा एक महिना बढी मान्य हुनुपर्छ। भुक्तानी व्यवस्थामा यी विधिका माइलस्टोन, मापनयोग्य नतिजा र प्रगतिका आधार पनि थपिन्छन्। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 15,20-21; base Rules 110(4) proviso,123(1)(च),124(2क2); pp.11,17-19
- Blacklisting notices may use email. If the person is not found at the office or home, or fails to explain within the email-notice period, the revised procedure requires a seven-day national-newspaper notice. Failure to explain does not itself require blacklisting: the Public Procurement Monitoring Office decides whether to blacklist using the public body’s detailed information and documents.कालोसूचीसम्बन्धी सूचना इमेलबाट पनि दिन सकिन्छ। व्यक्ति कार्यालय वा घरमा नभेटिए वा इमेल सूचनाको अवधिभित्र स्पष्टीकरण नदिए संशोधित प्रक्रियाले राष्ट्रियस्तरको पत्रिकामा सात दिनको सूचना माग्छ। स्पष्टीकरण नदिँदैमा कालोसूची अनिवार्य हुँदैन; सार्वजनिक खरिद अनुगमन कार्यालयले सार्वजनिक निकायको विस्तृत जानकारी र कागजातका आधारमा कालोसूचीमा राख्ने वा नराख्ने निर्णय गर्छ। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rule 22; base Rule 141(4),(4क),(5),(10क); pp.19-20
- The amendment also replaces “ten billion” with “twelve billion” in Rule 31च(4) and repeals Rule 97क. These textual changes are recorded without assigning broader effects to parent provisions not reproduced in this instrument. This explanation describes prescribed changes, not verified procurement practice, project outcomes or advice on a particular contract.संशोधनले नियम ३१च(४) को “दस अर्ब” लाई “बाह्र अर्ब” बनाउँछ र नियम ९७क खारेज गर्छ। यस दस्तावेजमा पूरा नदिइएका मूल व्यवस्थाको व्यापक प्रभाव निर्धारण नगरी यहाँ ती पाठगत परिवर्तन मात्र उल्लेख छन्। यो तोकिएका परिवर्तनको व्याख्या हो, प्रमाणित खरिद अभ्यास, आयोजनाका नतिजा वा कुनै खास सम्झौताको सल्लाह होइन। Government of Nepal, Department of Printing / Office of the Prime Minister and Council of Ministers Source accessed 2026-10-19 Amendment Rules 10,24; base Rules 31च(4),97क; pp.9,22
Gaps, loopholes and improvement ideas
A sourced assessment of gaps and improvement options is not published for this law yet. This does not establish that the law has no gaps.
Found a gap or loophole in this law? Propose an amendment →
Where does it conflict with other laws?
A provision-by-provision conflict assessment is not published for this law yet. This does not establish that it is consistent with every other law.
Catalogue check recorded 2026-10-18 · Scheduled catalogue check due 2026-11-17. This is the catalogue schedule, not a full review of this law. Individual source dates are shown below.
How we know this
- Department of Printing — Nepal Gazette (मुद्रण विभाग — नेपाल राजपत्र)मुद्रण विभाग: नेपाल राजपत्र 2082 — संख्या विषयसूची — publishes or lists it without stating its current status Checked 2026-10-11
The official listings we found do not agree on, or do not state, whether this law is in force, so its status is shown as not yet confirmed.
Policy Nepal publishes only what official records state. We do not invent or estimate facts; where a record is missing or unclear, we say so. Listings last compiled 2026-10-21. Our approach