Analysis drawn from official reports, court rulings and published research, each cited. Figures are being double-checked against the source documents; corrections are welcome.
What does it do?
- Public bodies must plan their purchases. A master procurement plan is required for projects lasting more than a year or for purchases of more than Rs 100 million a year, approved at a level that rises with the amount (from a second-class gazetted office chief up to Rs 250 million, to the ministry secretary above Rs 1 billion) and updated every year (Rule 7). Any body buying more than Rs 1 million a year must prepare an annual procurement plan with its budget, setting out packages, methods and timetables (Rule 8).सार्वजनिक निकायले खरिदको योजना बनाउनुपर्छ। एक वर्षभन्दा लामो अवधिसम्म चल्ने आयोजना वा वार्षिक रु. १० करोडभन्दा बढीको खरिदका लागि खरिदको गुरुयोजना बनाउनुपर्छ, जुन रकमअनुसार राजपत्राङ्कित द्वितीय श्रेणीको कार्यालय प्रमुखदेखि (रु. २५ करोडसम्म) मन्त्रालयको सचिवसम्म (रु. १ अर्बभन्दा बढी) स्वीकृत गर्छन् र प्रत्येक वर्ष अद्यावधिक गर्नुपर्छ (नियम ७)। वार्षिक रु. १० लाखभन्दा बढीको खरिद गर्ने निकायले बजेटसँगै खरिदको प्याकेज, विधि र समयतालिकासहितको वार्षिक खरिद योजना बनाउनुपर्छ (नियम ८)। Ministry of Law, Justice and Parliamentary Affairs Rules 7–8, PDF pp. 7–8
- Goods, works or services estimated at up to Rs 2 million may be bought through sealed quotations (up to Rs 5 million for X-ray, ECG, medicines and medical equipment), if fewer than three quotations come in after the first notice, a second notice is published, and the lowest quotation is chosen from the first call only if at least three are substantially responsive (Rule 84). Direct purchase is allowed up to Rs 1.5 million for works or goods and up to Rs 500,000 for consulting or other services, and no body may buy more than these limits from the same supplier in one year, whether at once or in several lots (Rule 85).रु. २० लाखसम्म लागत अनुमान भएको मालसामान, निर्माण कार्य वा सेवा सिलबन्दी दरभाउपत्रबाट खरिद गर्न सकिन्छ (एक्सरे, इसिजी, औषधिजन्य मालसामान र स्वास्थ्य उपकरणको हकमा रु. ५० लाखसम्म), पहिलो सूचनामा तीनभन्दा कम दरभाउपत्र परेमा दोस्रो पटक सूचना प्रकाशन गरिन्छ, र पहिलो सूचनाबाट न्यूनतम तीन वटा दरभाउपत्र सारभूत रूपमा प्रभावग्राही भएमा मात्र सबैभन्दा कम कबोल अङ्क भएको दरभाउपत्र छनोट गरिन्छ (नियम ८४)। रु. १५ लाखसम्मको निर्माण कार्य वा मालसामान र रु. ५ लाखसम्मको परामर्श वा अन्य सेवा सोझै खरिद गर्न सकिन्छ, तर एक आर्थिक वर्षमा एकै पटक वा पटक–पटक गरी एउटै व्यक्ति, फर्म वा संस्थाबाट यो सीमाभन्दा बढी सोझै खरिद गर्न पाइँदैन (नियम ८५)। Ministry of Law, Justice and Parliamentary Affairs Rules 84–85, PDF pp. 84–88
- Works or related services estimated at up to Rs 10 million may be given to a registered users' committee made up of local residents who will use the service (Rule 97). The public body must deduct VAT, overhead, contingency and the users' agreed contribution before paying; it may advance up to one-third of the contract amount; heavy machinery may not be used unless the cost estimate requires it and the body approves; and the committee must do the work itself, not through a contractor or subcontractor. A committee found using a contractor has its agreement cancelled, and the contractor is recommended for blacklisting.रु. १ करोडसम्म लागत अनुमान भएको निर्माण कार्य वा सोसम्बन्धी सेवा सोही स्थानमा बसोबास गर्ने र सेवा उपभोग गर्ने बासिन्दा मात्र रहेको दर्ता भएको उपभोक्ता समितिबाट गराउन सकिन्छ (नियम ९७)। सार्वजनिक निकायले भुक्तानी दिँदा मूल्य अभिवृद्धि कर, ओभरहेड, कन्टिन्जेन्सी र सम्झौताबमोजिमको जनसहभागिताको अंश कट्टा गर्नुपर्छ; सम्झौता रकमको बढीमा एक तिहाइसम्म पेस्की दिन सकिन्छ; लागत अनुमानमा उल्लेख भई निकायले सहमति नदिएसम्म हेभी मेसिन प्रयोग गर्न पाइँदैन; र समितिले आफूले पाएको काम निर्माण व्यवसायी वा सब–कन्ट्रयाक्टरबाट गराउन पाउँदैन। निर्माण व्यवसायी संलग्न गराएको पाइएमा सम्झौता रद्द गरी त्यस्तो निर्माण व्यवसायीलाई कालोसूचीमा राख्न सिफारिस गरिन्छ। Ministry of Law, Justice and Parliamentary Affairs Rule 97, PDF pp. 103–106
- If a contractor, supplier or consultant is late through its own fault, the contract may require liquidated damages of normally 0.05 per cent of the contract price per day, up to 10 per cent, and the contract must be ended if the work is still unfinished after that maximum period (Rule 121). Running bills must be approved and paid within 30 days, with 5 per cent kept back as retention money (Rule 123).आपूर्तिकर्ता, परामर्शदाता, सेवा प्रदायक वा निर्माण व्यवसायीको ढिलाइका कारण काम तोकिएको म्यादमा सम्पन्न नभएमा सम्झौताले साधारणतया प्रतिदिन सम्झौता रकमको ०.०५ प्रतिशत, बढीमा १० प्रतिशतसम्म पूर्वनिर्धारित क्षतिपूर्ति तोक्न सक्छ, र अधिकतम अवधिभित्र पनि काम सम्पन्न नभएमा सम्झौता अन्त्य गर्नुपर्छ (नियम १२१)। रनिङ बिल ३० दिनभित्र स्वीकृत गरी भुक्तानी गर्नुपर्छ र ५ प्रतिशत रिटेन्सन रकम कट्टा गरी राख्नुपर्छ (नियम १२३)। Ministry of Law, Justice and Parliamentary Affairs Rules 121 and 123, PDF pp. 128–129
- Besides its duties under Section 65 of the Act, the Public Procurement Monitoring Office monitors public bodies' procurement, sets up a central data bank of contract performance, plans for and checks the qualifications of procurement staff and evaluation committee members, monitors implementation of review committee decisions and reports to the Office of the Prime Minister and Council of Ministers, and runs training for procurement staff (Rule 144).ऐनको दफा ६५ मा उल्लिखित काम, कर्तव्य र अधिकारका अतिरिक्त सार्वजनिक खरिद अनुगमन कार्यालयले सार्वजनिक निकायको खरिद कारबाहीको अनुगमन गर्ने, खरिद सम्झौता कार्यान्वयनसम्बन्धी कार्यसम्पादनको अभिलेख राख्न केन्द्रीय डाटा बैङ्क स्थापना गर्ने, खरिद एकाइ र मूल्याङ्कन समितिका कर्मचारीको दक्षताको योजना बनाई यकिन गर्ने, पुनरावलोकन समितिको निर्णय कार्यान्वयनको अनुगमन गरी प्रधानमन्त्री तथा मन्त्रिपरिषद्को कार्यालयमा प्रतिवेदन दिने र खरिदमा संलग्न कर्मचारीलाई तालिम सञ्चालन गर्ने काम गर्छ (नियम १४४)। Ministry of Law, Justice and Parliamentary Affairs Rule 144, PDF pp. 139–140
Gaps, loopholes and improvement ideas
- Not enforced Liquidated damages under Rule 121 often go uncollected. Rule 121 and the contracts provide for liquidated damages of 0.05 per cent of the contract price per day, up to 10 per cent, when contractors finish late through their own fault. The Auditor General found that bodies under the ministries of Physical Infrastructure and Transport; Energy, Water Resources and Irrigation; Education, Science and Technology; and Defence had not collected Rs 2.08 billion of such damages (62nd report), and that bodies under the ministries of Physical Infrastructure and Transport, Drinking Water, Urban Development and Defence had not collected Rs 199.80 million on 19 contracts (63rd report).नियम १२१ बमोजिमको पूर्वनिर्धारित क्षतिपूर्ति धेरै ठेक्कामा असुल भएको छैन। निर्माण व्यवसायीको ढिलाइले काम समयमा सम्पन्न नभएमा प्रतिदिन सम्झौता मूल्यको ०.०५ प्रतिशतका दरले बढीमा १० प्रतिशतसम्म पूर्वनिर्धारित क्षतिपूर्ति लिनुपर्ने व्यवस्था नियम १२१ र खरिद सम्झौतामा छ। भौतिक पूर्वाधार तथा यातायात, ऊर्जा, जलस्रोत तथा सिँचाइ, शिक्षा, विज्ञान तथा प्रविधि र रक्षा मन्त्रालयअन्तर्गतका निकायले रु. २ अर्ब ८ करोड १५ लाख १५ हजार (बासट्ठीऔँ प्रतिवेदन), र भौतिक पूर्वाधार तथा यातायात, खानेपानी, सहरी विकास र रक्षा मन्त्रालयअन्तर्गतका निकायले १९ ठेक्कामा रु. १९ करोड ९७ लाख ९७ हजार (त्रिसट्ठीऔँ प्रतिवेदन) पूर्वनिर्धारित क्षतिपूर्ति असुल नगरेको महालेखापरीक्षकले औँल्याएका छन्। Office of the Auditor General, Nepal · Office of the Auditor General, Nepal OAG 62nd Annual Report, chapter 3 (summary of main findings), para 72, printed p. 39 (PDF p. 67); OAG 63rd Annual Report, chapter 3, para 44, printed p. 30 (PDF p. 60)
- Not enforced Rule 97 is often breached when local governments use users' committees. The rule is meant for labour-based work done by the committee itself, with the users' contribution deducted before payment and no contractors. In FY 2081/82 the Auditor General found that 265 local governments had given 1,636 technically complex works worth Rs 2.69 billion to users' committees; 85 had paid Rs 60.69 million on 690 projects without deducting the users' share; and 143 had paid Rs 710.81 million for 1,014 projects whose work was actually done by contractors (the year before, 118 local governments paid Rs 898.36 million for 1,791 such projects). The High-Level Economic Reform Suggestion Commission, citing the Public Procurement Monitoring Office, also lists users' committees having contractors do their work among the irregularities in the construction sector.स्थानीय तहले उपभोक्ता समितिमार्फत काम गराउँदा नियम ९७ धेरैपटक पालना भएको छैन। यो नियम उपभोक्ता समिति आफैँले गर्ने श्रममूलक कामका लागि हो, जसमा भुक्तानी दिँदा जनसहभागिताको अंश कट्टा गर्नुपर्छ र निर्माण व्यवसायी संलग्न गराउन पाइँदैन। आर्थिक वर्ष २०८१/८२ मा २६५ स्थानीय तहले जटिल प्राविधिक पक्ष भएका १,६३६ निर्माण कार्य उपभोक्ता समितिमार्फत गराई रु. २ अर्ब ६९ करोड ६ लाख १३ हजार खर्च गरेको, ८५ स्थानीय तहले ६९० योजनामा उपभोक्ताको अंश कट्टा नगरी रु. ६ करोड ६ लाख ९२ हजार भुक्तानी गरेको, र १४३ स्थानीय तहले उपभोक्ता समितिले गर्नुपर्ने १,०१४ योजनाको काम निर्माण व्यवसायीबाट गराएको बिल पेस गरी रु. ७१ करोड ८ लाख ९ हजार भुक्तानी गरेको महालेखापरीक्षकले देखाएका छन् (अघिल्लो वर्ष ११८ स्थानीय तहले १,७९१ योजनामा रु. ८९ करोड ८३ लाख ५८ हजार भुक्तानी गरेका थिए)। सार्वजनिक खरिद अनुगमन कार्यालयलाई उद्धृत गर्दै उच्चस्तरीय आर्थिक सुधार सुझाव आयोगले पनि उपभोक्ता समितिले जिम्मा लिई निर्माण व्यवसायीबाट काम गराउने प्रवृत्तिलाई निर्माण क्षेत्रको अनियमितताका रूपमा उल्लेख गरेको छ। Office of the Auditor General, Nepal · Office of the Auditor General, Nepal OAG 63rd Annual Report, local government section, paras 35–37, printed pp. 919–920 (PDF pp. 973–974); OAG 62nd Annual Report, section 4 (local governments), para 45, printed p. 888 (PDF p. 928); HLERC report, public procurement section, para 22, printed p. 248 (PDF p. 315)
- Capacity The Public Procurement Monitoring Office has not carried out several duties under Rule 144 and lacks capacity. The Auditor General found that it had not certified procurement experts, set up a central data bank recording contract performance, or drafted a procurement code of conduct. The Office's own monitoring of 35 public bodies, including 14 local governments in 17 districts, found procurement staff lacking training, the Rule 7 master procurement plan not prepared for purchases above Rs 100 million a year, the same staff serving repeatedly on procurement units and evaluation committees, and office chiefs themselves named as heads of procurement units. The Auditor General said the Office lacks the institutional capacity and skilled staff to train procurement staff in the numbers needed from the centre down to local governments.सार्वजनिक खरिद अनुगमन कार्यालयले नियम १४४ बमोजिमका केही जिम्मेवारी पूरा गरेको छैन र यसको क्षमता अपुग छ। खरिद विज्ञ प्रमाणीकरण, खरिद सम्झौता कार्यान्वयनको अभिलेख राख्ने केन्द्रीय डाटा बैङ्क र खरिद आचारसंहिता तर्जुमा जस्ता काम नभएको महालेखापरीक्षकले औँल्याएका छन्। कार्यालयले १७ जिल्लाका १४ स्थानीय तहसहित ३५ सार्वजनिक निकायको अनुगमन गरी तयार गरेको प्रतिवेदनमा खरिदमा संलग्न जनशक्तिमा तालिमको अभाव, वार्षिक रु. १० करोडभन्दा बढीको खरिदमा नियम ७ बमोजिम गुरुयोजना नबनाइएको, खरिद एकाइ र मूल्याङ्कन समितिमा एउटै कर्मचारी दोहोरिएको र कार्यालय प्रमुख नै खरिद एकाइ प्रमुख तोकिएको देखिएको छ। केन्द्रदेखि स्थानीय तहसम्म मागअनुसार तालिम दिन कार्यालयको संस्थागत क्षमता र दक्ष जनशक्ति कम रहेको महालेखापरीक्षकको भनाइ छ। Office of the Auditor General, Nepal OAG 63rd Annual Report, Office of the Prime Minister and Council of Ministers chapter (Public Procurement Monitoring Office), paras 7 and 13, printed pp. 87 and 89 (PDF pp. 119 and 121)
Ideas to fix it
- Strengthen the Public Procurement Monitoring Office's institutional capacity, and set up a standing mechanism for capacity-building training and problem-solving for staff involved in procurement.सार्वजनिक खरिद अनुगमन कार्यालयको संस्थागत क्षमता सुदृढ गर्ने, र खरिदमा संलग्न जनशक्तिको व्यावसायिक क्षमता विकास तालिम तथा समस्या समाधानका लागि स्थायी संयन्त्र बनाउने। Proposed by: Office of the Auditor General Office of the Auditor General, Nepal
- Develop procurement management as a separate service: give every office a procurement management unit, let only certified procurement experts carry out procurement, strengthen the Public Procurement Monitoring Office, and set separate procurement standards for different kinds of goods and services.खरिद व्यवस्थापनलाई छुट्टै सेवाका रूपमा विकास गर्ने: प्रत्येक कार्यालयमा खरिद व्यवस्थापन एकाइ राख्ने, प्रमाणित खरिद विज्ञबाट मात्र खरिद कार्य सञ्चालन गर्ने, सार्वजनिक खरिद अनुगमन कार्यालयको संस्थागत सुदृढीकरण गर्ने, र वस्तु तथा सेवाको प्रकृतिअनुसार अलग–अलग खरिद मापदण्ड बनाउने। Proposed by: High-Level Economic Reform Suggestion Commission High-Level Economic Reform Commission (उच्चस्तरीय आर्थिक सुधार सुझाव आयोग), submitted to the Ministry of Finance
- To reduce the rush of payments at the end of the fiscal year, pay contractors within 15 days after the work is complete and the bill is issued. (Rule 123(3) currently allows up to 30 days to approve and pay a running bill.)आर्थिक वर्षको अन्त्यमा भुक्तानी गर्ने प्रवृत्ति घटाउन काम सम्पन्न भई बिल–बीजक जारी भएको १५ दिनभित्र भुक्तानी गर्ने। (हाल नियम १२३(३) ले रनिङ बिल स्वीकृत गरी भुक्तानी गर्न ३० दिनसम्मको समय दिएको छ।) Proposed by: High-Level Economic Reform Suggestion Commission High-Level Economic Reform Commission (उच्चस्तरीय आर्थिक सुधार सुझाव आयोग), submitted to the Ministry of Finance · Ministry of Law, Justice and Parliamentary Affairs
Where does it conflict with other laws?