Price adjustment in design-and-build contracts: the Act bars it for lump-sum contracts, the Rules now build it into cost estimates
Section 55(2) of the Public Procurement Act 2063 says price adjustment may not be made where a contract is on a lump-sum or fixed-budget basis. The Act does not say whether design-and-build contracts are lump-sum. The Auditor General found that, before a 2082 rule change, 22 offices paid Rs 44.86 crore of price adjustment on 75 design-and-build contracts that it considered lump-sum, and so not eligible. The 14th amendment to the Public Procurement Rules (2082/1/15) now includes a 10 per cent price-adjustment contingency in the design-and-build cost-estimate format.
Laws and sections involved
- Public Procurement Act, 2063 s.55(1) and proviso, (1क), (1ख), (2)
Our paraphrase: unless the contract provides otherwise, price adjustment may be made in contracts longer than twelve months (s.55(1)); for works procured through national-level bidding, if the price of a construction material unexpectedly moves by more than 10 per cent after the contract, the change beyond 10 per cent shall be adjusted as prescribed (proviso to s.55(1)); a special price adjustment may be made under a Cabinet-approved procedure for abnormal cost increases from war, pandemic, blockade and similar causes (s.55(1क)–(1ख), added by the Second Amendment Act 2083); but price adjustment may not be made where delay is the contractor's fault or where the contract is on a lump-sum ('lump sum contract') or fixed-budget basis (s.55(2)).
Law Commission consolidated text (authenticated 2063/09/30); five amending Acts listed, the latest the Public Procurement (Second Amendment) Act 2083 (2083/03/25), which followed the Second Amendment Ordinance 2083 (Gazette 2083/01/17). s.55 on PDF pp.55–56. Official text - Public Procurement Regulation, 2064 r.2(य), 2(र) (definitions); r.10(8); r.22(3); r.119; Schedule 1ख; Schedule 4, items (ख) and (ङ)
Our paraphrase: a design-and-build contract is one under which the same contractor does design and construction (r.2(य)); cost estimates for design-and-build works must follow Schedule 1ख (r.10(8)); Schedule 1ख adds a "price adjustment contingency" of 10 per cent to the estimate; r.119 requires any contract allowing price adjustment to state the conditions, formula and cap (normally 25 per cent of contract value); public bodies may use design-and-build for medium, large and complex infrastructure (Schedule 4, item (ङ)), which the Schedule lists separately from the lump-sum contract (item (ख)). By contrast, r.22(3) says procurement through EPC contracts must be on a lump-sum basis; the Rules say no such thing about design-and-build.
Law Commission consolidated text (2064/05/03), amended sixteen times, the latest the 16th amendment (2083/05/03); the 14th amendment (2082/01/15) is the change the Auditor General refers to. r.2(य) PDF p.4; r.10(8) PDF p.12; r.119 PDF pp.143–144; Schedule 1ख PDF p.176; contract-type item (ङ) PDF p.188. Official text
The apparent issue
The Act bars price adjustment for lump-sum contracts but does not define whether design-and-build contracts are lump-sum. The Auditor General treats them as lump-sum; contracting offices had included price adjustment clauses; and the Rules, since 2082, add a price-adjustment contingency to design-and-build cost estimates. If design-and-build contracts are lump-sum, a rule that budgets for price adjustment in them may sit uneasily with s.55(2), since rules cannot override the Act. The structure of the Rules cuts against treating every design-and-build contract as lump-sum: they list design-and-build separately from lump-sum contracts and require only EPC contracts to be lump-sum. But that structure dates at least from the 14th amendment, and the earlier text that governed the contracts the Auditor General examined was not seen.
Evidence
- The Auditor General reported that the Act and Rules did not spell out how price adjustment applies to design-and-build procurement, that the Public Procurement Monitoring Office had not prepared bidding documents for it, and that the Public Accounts Committee had directed further legal provision on variations and price adjustment. It said the 14th amendment to the Rules on 2082/01/15 set a cost-estimate format in Schedule 1(ख) that includes the price adjustment amount for design-and-build contracts. Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय Chapter 3 (summary of main audit findings), para 39, printed pp.28–29 (PDF pp.58–59)
- For contracts signed before that amendment, the Auditor General found that 22 offices under the Ministry of Physical Infrastructure and Transport paid Rs 44.86 crore of price adjustment on 75 design-and-build contracts, and said that because these are lump-sum contracts, payment does not appear permissible under the Act. Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय Para 39, printed pp.28–29 (PDF pp.58–59)
- s.55 of the Act and r.2(य), r.10(8), r.119 and Schedule 1ख of the Rules were read in the Law Commission texts. The Rules define design-and-build by who performs the work, not by payment basis, and neither text states that design-and-build contracts are lump-sum. Nepal Law Commissionनेपाल कानून आयोग Act PDF pp.55–56; Rules PDF pp.4, 12, 143–144, 176
- In the consolidated Rules, r.22(3) requires EPC procurement to be on a lump-sum basis, and Schedule 4 lists the lump-sum contract (item (ख)) and the design-and-build contract (item (ङ), as amended by the 14th amendment) as separate contract types. Neither provision says design-and-build contracts are lump-sum. Nepal Law Commissionनेपाल कानून आयोग Rules PDF p.23 (r.22(3)); PDF pp.187–188 (Schedule 4)
Possible readings
- Reading 1 (the Auditor General's view): design-and-build contracts are lump-sum by nature, so s.55(2) bars price adjustment in them; contract clauses or rules providing otherwise cannot override the Act.
- Reading 2: "design-and-build" describes who designs and builds, not how the price is set; such a contract can be lump-sum or re-measured. Where it is not lump-sum and runs over twelve months, s.55(1) allows price adjustment, and the 2082 Rules simply ensure it is budgeted.
- Reading 3: s.55(1) begins "unless the contract provides otherwise", so the parties' contract decides; payments made under contracts that expressly included price adjustment may be defensible even if the contract was described as design-and-build, though s.55(2) may still prevail for a true lump-sum contract.
Why does it matter in practice?
Uncertainty can lead to inconsistent contract terms, audit objections (beruju), disputes and arbitration, and either overpayment to contractors or unfair risk for them when material prices rise sharply. The new special price-adjustment power in s.55(1क) adds a further route whose relationship with s.55(2) is also not spelled out.
Hypothetical example
Hypothetical: a road office signs a three-year design-and-build contract for a bridge. Steel prices rise 30 per cent in year two. The contractor claims price adjustment under a clause in the contract; the auditor says s.55(2) bars it because the contract is lump-sum; the contractor points to the Rules' price-adjustment contingency and to s.55(1).
Possible improvements and trade-offs
- Amend s.55 to state expressly whether, and on what conditions, price adjustment applies to design-and-build and EPC contracts.
Settles the question at the level of the Act; requires a policy choice on risk-sharing for long contracts. - Have the Public Procurement Monitoring Office issue standard design-and-build bidding documents that state the payment basis and any price-adjustment formula.
Practical and fast (the Auditor General noted these were missing); cannot resolve a conflict with the Act if one exists. - Decide how to treat payments already made under pre-2082 contracts (recovery, regularisation or case-by-case review).
Resolves audit objections; recovery may lead to disputes with contractors.
Questions for legal review
- Is a design-and-build contract a "lump-sum contract" within s.55(2) of the Act, or does that depend on the payment terms of each contract?
- Is the 10 per cent price-adjustment contingency in Schedule 1ख consistent with s.55(2)?
- Does the special price adjustment in s.55(1क) apply to lump-sum contracts despite s.55(2)?
- Before the 14th amendment (2082/01/15), did the Rules already treat design-and-build as a contract type separate from lump-sum? If so, can the Auditor General's view that design-and-build is lump-sum by nature be supported for the pre-2082 contracts?
Research status
Library check recorded 2026-10-11 · Scheduled library check due 2026-11-10. This is the source-library schedule, not a legal review of this research candidate. Individual source dates are shown below.
- Researched
- 2026-10-12
- Confidence
- Medium confidence — The provisions were read in the official texts and the Auditor General documents the problem and the amounts. Confidence is not high because the Rules' contingency could be read as consistent with the Act (Reading 2), and the 2083 amendments and any Monitoring Office guidance after 2082 were not reviewed in full.
- Review
- Not yet reviewed by a qualified lawyer.
Still unresolved
- Whether the Public Procurement Monitoring Office has since issued design-and-build bidding documents was not checked.
- The Second Amendment Act 2083 text itself was not read; we relied on the consolidated Act.
- No court or arbitration decision on this point was searched for.
- The pre-2082 wording of Schedule 4 item (ङ) and of r.22 (before the 14th amendment) was not seen.
AI research review (not legal advice)
An AI research assistant checked the cited sources and the reasoning for Policy Nepal. This is not legal advice and does not replace review by a qualified lawyer, which is still pending.
- Result of the AI check
- Narrowed after source checks
- AI check date
- 2026-10-25
Section 55 of the Act, the Rules (definitions, r.10(8), r.22, r.119, Schedules 1ख and 4) and the Auditor General's para 39 were re-read on official hosts; the figures, dates and locators are accurate. The reasoning was narrowed: the current Rules list design-and-build separately from lump-sum contracts and require only EPC to be lump-sum, which makes the Auditor General's 'lump-sum by nature' premise more contestable. Confidence stays medium.
Checks made (7)
- Confirmed in the cited source: Act title page: five amending Acts, incl. the Act Amending Some Nepal Acts 2082 (2082/04/14) and the Second Amendment Act 2083 (2083/03/25). s.55(1), (1क), (1ख) and (2) read on PDF pp.55–56; (1क)–(1ख) are footnoted as added by the Second Amendment. The quoted s.55(2) words match.
- Corrected after checking: The proviso to s.55(1) (adjustment of material price changes beyond 10 per cent for works procured by national-level bidding, 'shall' be made) was missing from the paraphrase and was added; it is also subject to s.55(2)'s 'notwithstanding subsection (1)'.
- Confirmed in the cited source: Auditor General 63rd report, Chapter 3, para 39, printed pp.28–29 (PDF pp.58–59) read: 22 offices, 75 contracts, Rs 44,85,63,000; the 14th amendment of 2082/01/15 set Schedule 1(ख); the Auditor General calls design-and-build 'lump-sum in nature'. As described.
- Confirmed in the cited source: Rules title page: sixteen amendments, the 14th on 2082/01/15 and the 16th on 2083/05/03. r.2(य) (PDF p.4), r.10(8) (PDF p.12), r.119 incl. the normal 25 per cent cap (PDF pp.143–144) and Schedule 1ख with a 10 per cent price-adjustment contingency (total estimate 1.24 × subtotal, PDF p.176) read as described.
- Reasoning narrowed: r.22(3) (PDF p.23) requires EPC procurement to be lump-sum, and Schedule 4 (PDF pp.187–188) lists lump-sum (ख) and design-and-build (ङ) as separate types. Schedule 1ख builds the estimate from item rates times quantities. Together these support Reading 2 for contracts under the current Rules, so the reasoning was narrowed.
- Not confirmed from the source: Schedule 4 item (ङ) carries a footnote saying it was amended by the 14th amendment; the earlier wording that governed the contracts the Auditor General examined was not seen.
- Not confirmed from the source: Not checked: Public Procurement Monitoring Office standard design-and-build documents, the Second Amendment Act 2083 as enacted (only the consolidated text), and court or arbitration decisions.
Open questions for a lawyer
- Does s.55(2) ('notwithstanding subsection (1)') also limit the special price adjustment in s.55(1क), which itself begins 'notwithstanding anything in subsection (1)'?
- If a design-and-build contract has a fixed total price paid by milestones but also contains an express price-adjustment clause, is it a 'lump sum contract' within s.55(2)?
- How do the mandatory proviso to s.55(1) for national-level bidding and the bar in s.55(2) interact for design-and-build works?
The Nepali text of this AI review is a draft awaiting native review.
How we know this
- Office of the Auditor General, Nepalमहालेखा परीक्षकको कार्यालय: महालेखापरीक्षकको त्रिसट्ठीऔँ वार्षिक प्रतिवेदन, २०८३ (63rd Annual Report of the Auditor General, 2083) Checked 2026-10-11
- Nepal Law Commission, Government of Nepalनेपाल कानून आयोग: सार्वजनिक खरिद ऐन, २०६३ (Public Procurement Act, 2063) — consolidated Nepali text Checked 2026-10-11
- Nepal Law Commission, Government of Nepalनेपाल कानून आयोग: सार्वजनिक खरिद नियमावली, २०६४ (Public Procurement Rules, 2064) — consolidated Nepali text Checked 2026-10-11
Every statement on this page links to the source above. We do not invent or estimate facts: official records lead for official acts, other sources are named for what they are, and where a record is missing or unclear, we say so. Our approach