Analysis drawn from official reports, court rulings and published research, each cited. Figures are being double-checked against the source documents; corrections are welcome.
What does it do?
- The Act governs infrastructure and service projects built through public-private partnership (PPP) or wholly private investment. Responsibility depends on size: local governments handle projects within their remit, provincial governments theirs, federal ministries federal projects up to Rs 6 billion (or hydropower and energy up to 200 MW), and the Investment Board Nepal anything larger. PPP may take forms such as build-operate-transfer, lease-operate-transfer or rehabilitate-operate-transfer; projects that transfer no real risk to the private side, or that concern national security, may not be done as PPP.सार्वजनिक-निजी साझेदारी वा पूर्ण निजी लगानीबाट बन्ने पूर्वाधार तथा सेवा परियोजना यस ऐनले नियमन गर्छ। जिम्मेवारी परियोजनाको आकारअनुसार बाँडिएको छ: स्थानीय तहका कार्यक्षेत्रका परियोजना स्थानीय तहले, प्रदेशका प्रदेश सरकारले, सङ्घका ६ अर्ब रुपैयाँसम्मका (जलविद्युत् र ऊर्जा भए २०० मेगावाटसम्मका) परियोजना सम्बन्धित मन्त्रालयले, र त्योभन्दा ठूला परियोजना लगानी बोर्ड नेपालले कार्यान्वयन गर्छन्। साझेदारी निर्माण-सञ्चालन-हस्तान्तरण, लिज-सञ्चालन-हस्तान्तरण, पुनर्स्थापना-सञ्चालन-हस्तान्तरण जस्ता ढाँचामा हुन सक्छ; निजी पक्षमा वास्तविक जोखिम नसर्ने वा राष्ट्रिय सुरक्षासँग सम्बन्धित परियोजना साझेदारीबाट गर्न पाइँदैन। Nepal Law Commission Section 2(b), p. 4; Sections 3–4, pp. 4–5; Sections 17–18, pp. 15–16
- The Investment Board, chaired by the Prime Minister with the Finance Minister as vice-chair, other ministers, the National Planning Commission vice-chair, the Nepal Rastra Bank governor, the Chief Secretary and three experts (at least one a woman), approves large investments and sets PPP priorities; its office, led by a chief executive officer, includes PPP and investment-promotion directorates and a one-stop service centre where agencies must post staff with decision-making authority to give registrations, permits, visas, land and environmental approvals.प्रधानमन्त्रीको अध्यक्षता र अर्थमन्त्रीको उपाध्यक्षतामा अन्य मन्त्री, राष्ट्रिय योजना आयोगका उपाध्यक्ष, नेपाल राष्ट्र बैङ्कका गभर्नर, मुख्य सचिव र कम्तीमा एक महिलासहित तीन विज्ञ रहने लगानी बोर्डले ठूला लगानी स्वीकृत गर्छ र साझेदारीका प्राथमिकता तोक्छ। प्रमुख कार्यकारी अधिकृतको नेतृत्वमा रहने बोर्डको कार्यालयमा सार्वजनिक-निजी साझेदारी निर्देशनालय, लगानी प्रवर्द्धन निर्देशनालय र एकल बिन्दु सेवा केन्द्र रहन्छन्; केन्द्रमा सम्बन्धित निकायले निर्णय गर्ने अधिकारसहितका कर्मचारी खटाई दर्ता, अनुमति, भिसा, जग्गा र वातावरणीय स्वीकृति दिलाउनुपर्छ। Nepal Law Commission Sections 5–8, pp. 5–9; Sections 10–15, pp. 10–15; Section 46, pp. 25–26
- Agencies must identify and get approval for PPP projects, publish the list, and select investors competitively through expressions of interest and proposals evaluated on technical merit, royalty and user charges. Unsolicited proposals may be accepted and put to a 'Swiss challenge'; direct negotiation is allowed if two rounds of competition fail or for reasons such as new technology or national priority. Selected investors receive a licence and sign a project agreement, which can be cancelled for breach.सम्बन्धित निकायले साझेदारी परियोजना पहिचान गरी स्वीकृत गराउनुपर्छ, सूची प्रकाशित गर्नुपर्छ, र आशयपत्र तथा प्रस्ताव आह्वान गरी प्राविधिक पक्ष, रोयल्टी र उपभोक्ता महसुलका आधारमा प्रतिस्पर्धाबाट लगानीकर्ता छान्नुपर्छ। आह्वान नगरिएको प्रस्ताव पनि लिन सकिन्छ र त्यसलाई "स्विस च्यालेन्ज" मार्फत प्रतिस्पर्धामा लैजान सकिन्छ; दुईपटक आह्वान गर्दा पनि छनोट नभए वा नयाँ प्रविधि, राष्ट्रिय प्राथमिकता जस्ता कारणले सोझै वार्ताबाट पनि कार्यान्वयन गर्न सकिन्छ। छानिएका लगानीकर्ताले अनुमतिपत्र पाउँछन् र परियोजना सम्झौता गर्नुपर्छ, जुन उल्लङ्घन भए रद्द गर्न सकिन्छ। Nepal Law Commission Sections 20–31, pp. 16–21; Sections 37–39, pp. 21–23
- Licensed projects get the incentives available under other laws plus any the Board recommends, a Viability Gap Fund for important but not immediately profitable projects, and guarantees: no nationalisation, no expropriation except for public purpose with due process, protection from later adverse legal or policy changes during the licence, and foreign-exchange conversion for repaying foreign loans and repatriating returns. Investors must arrange land themselves (with facilitation), pay royalty and hand the project back in working condition at the end. Disputes with foreign investors go to negotiation and then arbitration in Nepal under UNCITRAL rules unless agreed otherwise.अनुमतिपत्र पाएका परियोजनाले अन्य कानूनबमोजिमका सुविधाका अतिरिक्त बोर्डले सिफारिस गरेका थप सुविधा पाउँछन्; महत्त्वपूर्ण तर तत्काल नाफामूलक नभएका परियोजनाका लागि सम्भाव्यता न्यून परिपूरक कोष (भायबिलिटी ग्याप फन्डिङ) रहन्छ; र राष्ट्रियकरण नगरिने, सार्वजनिक प्रयोजनबाहेक र उचित प्रक्रियाबिना अधिग्रहण नगरिने, अनुमतिपत्र अवधिभर प्रतिकूल कानूनी वा नीतिगत परिवर्तन लागू नहुने, र विदेशी ऋण तिर्न तथा प्रतिफल फिर्ता लैजान सटही सुविधा पाइने प्रत्याभूति छ। जग्गा लगानीकर्ता आफैँले (सहजीकरणसहित) जुटाउनुपर्छ, रोयल्टी तिर्नुपर्छ र अवधि सकिएपछि परियोजना चालू हालतमा हस्तान्तरण गर्नुपर्छ। विदेशी लगानीसम्बन्धी विवाद पहिले वार्ता र त्यसपछि अन्यथा सहमति नभए अन्सिट्रल नियमअनुसार नेपालमै मध्यस्थताबाट समाधान हुन्छ। Nepal Law Commission Sections 41–45, pp. 24–25; Section 47, p. 26; Sections 54–56, p. 29; Section 65, p. 32
Gaps, loopholes and improvement ideas
- Capacity Projects are put to investors without proper preparation. Section 8 makes the Board responsible for collecting project details, studying projects and preparing the project list. The Auditor General found that the Investment Board office had been inviting expressions of interest and proposals without detailed project studies, and investor interest was low: of 19 projects showcased at the third investment summit (Baisakh 2081), only two drew expressions of interest.पर्याप्त तयारीबिनै परियोजना लगानीकर्तासामु लगिन्छ। दफा ८ ले परियोजनाको विवरण सङ्कलन, अध्ययन र सूची तयार गर्ने जिम्मा बोर्डलाई दिएको छ। महालेखापरीक्षकका अनुसार लगानी बोर्डको कार्यालयले परियोजनाको विस्तृत अध्ययनबिनै आशयपत्र र प्रस्ताव आह्वान गर्दै आएकोले लगानीकर्ताको चासो न्यून देखियो: तेस्रो लगानी सम्मेलन (२०८१ वैशाख) मा प्रस्तुत १९ परियोजनामध्ये २ मा मात्र आशयपत्र प्राप्त भयो। Office of the Auditor General, Nepal · Nepal Law Commission OAG 62nd report, OPMCM chapter (Investment Board), para 31, printed p. 92 (PDF p. 122); PPP Act s. 8, pp. 6–9
- Capacity Some approved projects have not yet moved forward, mostly over land. The Auditor General reported that the Board had approved Rs 1,293 billion of investment in 38 projects (11 non-energy, 27 energy), but only two cement plants were producing and three hydropower projects (Arun 3, Upper Trishuli 1, Upper Karnali) were under construction. Problems listed included unresolved land-ceiling exemptions and leases of government and forest land (Arun 3, Upper Karnali), pending land acquisition (Lower Arun), unclear hedging liability (Upper Myagdi 2), unappointed negotiating-committee members (a Kapilvastu–Banke solar project) and lack of coordination among Kathmandu Valley local levels on an integrated waste-management project.केही स्वीकृत परियोजना अझै अघि बढ्न सकेका छैनन्, धेरैजसो जग्गाका कारण। महालेखापरीक्षकका अनुसार बोर्डले ११ गैरऊर्जा र २७ ऊर्जासहित ३८ परियोजनामा रु. १२ खर्ब ९३ अर्ब लगानी स्वीकृत गरेकोमा दुई सिमेन्ट उद्योग मात्र उत्पादनमा र तीन जलविद्युत् आयोजना (अरुण ३, माथिल्लो त्रिशूली १, माथिल्लो कर्णाली) निर्माणमा थिए। समस्यामा जग्गा हदबन्दी छुट र सरकारी तथा वन जग्गाको लिज नटुङ्गिएको (अरुण ३, माथिल्लो कर्णाली), जग्गा प्राप्ति बाँकी (तल्लो अरुण), हेजिङ दायित्व अस्पष्ट (माथिल्लो म्याग्दी २), वार्ता समितिमा सदस्य मनोनयन नभएको (कपिलवस्तु–बाँके सौर्य आयोजना) र काठमाडौँ उपत्यकाका स्थानीय तहबीच समन्वय नभएको (एकीकृत फोहोरमैला व्यवस्थापन) उल्लेख छन्। Office of the Auditor General, Nepal · Nepal Law Commission OAG 62nd report, OPMCM chapter (Investment Board), para 32 and project table, printed pp. 93–94 (PDF pp. 123–124); PPP Act ss. 4(1)(d), 46–47, pp. 4, 25–26
- Not enforced Competitive licensing of energy projects under the Act has not delivered. The Auditor General noted that although projects in the Department of Electricity Development's project bank were to be licensed to private developers competitively with an upfront fee under the PPP and Investment Act, the projects had not been implemented that way.ऐनअन्तर्गत ऊर्जा आयोजना प्रतिस्पर्धाबाट दिने व्यवस्था कार्यान्वयन भएको छैन। विद्युत् विकास विभागको आयोजना बैङ्कका आयोजना सार्वजनिक-निजी साझेदारी तथा लगानी ऐनबमोजिम अग्रिम शुल्क लिई प्रतिस्पर्धाका आधारमा निजी उत्पादकलाई दिने व्यवस्था भए पनि त्यसअनुरूप कार्यान्वयन हुन नसकेको महालेखापरीक्षकले उल्लेख गरेका छन्। Office of the Auditor General, Nepal · Nepal Law Commission OAG 63rd report, Ministry of Energy, Water Resources and Irrigation chapter (Department of Electricity Development), project bank paragraph, printed pp. 207–208 (PDF pp. 239–240); PPP Act ss. 23–27, pp. 17–18
Where does it conflict with other laws?
No conflict with another law is documented in the sources we have reviewed so far.