North–South (Koshi) Road Projectउत्तर दक्षिण (कोशी) सडक योजना
Under constructionनिर्माणाधीन Roadsसडक
Facts are shown in the language of the official source they come from. Each figure gives the date it describes.
What is it?
- “कोशी कोरिडोर (१६२ किलोमिटर)” (as of 2082/83) Ministry of Financeअर्थ मन्त्रालय Economic Survey 2082/83 (Nepali), PDF p.186 (printed p.१५२), para १०.१०
When will it be finished?
- Started
- “२०६५/६६” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'आयोजना शुरु आ.व.'
- First planned completion
- “२०७९।८० मा सम्पन्न हुने अनुमान रहेकोमा” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.3
Other official figures: “२०७९/८०” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row ११ - Revised completion
- “हाल २०८५।८६ मा सम्पन्न गर्ने लक्ष्य रहेको छ।” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.3
- Revised completion
- “२०८३/८४” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row ११, column 'संशोधित'
- Official statement on completion
- “२०६५/६६ - २०८५/८६” (as of MTEF 2083/84) National Planning Commissionराष्ट्रिय योजना आयोग MTEF PDF p.302 (printed p.२९५), budget head ३३७०१११८, column 'आयोजना अवधि (सुरु समाप्ति)'
- Revised completion
- “२०८५/८६” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'आयोजना सम्पन्न हुने आ.व.'
- Behind the first plan
- 6 Bikram Sambat years Calculated by Policy Nepal from the two official figures shown.
What does it cost?
- First cost estimate
- Rs 11.9 billionरु. ११.९ अर्ब · “११९३ (रु.करोडमा)” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'आयोजना लागत अनुमान (रु.करोडमा) | शुरु लागत अनुमान'
Other official figures: “रु.११ अर्ब ९३ करोड लागतमा सुरु भएको” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.3; “१,२५४.९०” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row ११, column 'आयोजनाको सुरूको लागत' - Revised cost estimate
- Rs 16.2 billionरु. १६.२ अर्ब · “संशोधित लागत अनुमान रु.१६ अर्ब २० करोड” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.3
- Revised cost estimate
- Rs 16.8 billionरु. १६.८ अर्ब · “१,६८२.९०” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row ११, column 'संशोधित लागत'
- Revised cost estimate
- Rs 74.9 billionरु. ७४.९ अर्ब · “७४८६००” (as of MTEF 2083/84) National Planning Commissionराष्ट्रिय योजना आयोग MTEF PDF p.302 (printed p.२९५), budget head ३३७०१११८ 'उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column 'लागत (रु लाखमा)'
- Revised cost estimate
- Rs 16.2 billionरु. १६.२ अर्ब · “१६२० (रु.करोडमा)” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'आयोजना लागत अनुमान (रु.करोडमा) | संशोधित लागत अनुमान'
- Spent so far
- Rs 6.7 billionरु. ६.७ अर्ब · “यस वर्षको रु.१ अर्ब १० करोडसमेत रु.६ अर्ब ६८ करोड खर्च” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.3
- Spent so far
- Rs 6.7 billionरु. ६.७ अर्ब · “६६८ (रु.करोडमा)” (from project start to FY 2081/82मिति आयोजना शुरु भएदेखि आ.व. २०८१/८२ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'कुल खर्च (रु.करोडमा)'
- Spent so far
- Rs 7.3 billionरु. ७.३ अर्ब · “७२८ (रु.करोडमा)” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'कुल खर्च (रु.करोडमा)'
Budget each year
| Fiscal year | Figure | Source |
|---|---|---|
| 2081/82 | Rs 5.2 billionरु. ५.२ अर्ब ५,२१,६३ रु. लाख | Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84, PDF p.395 (printed p.३७३), budget head row '३३७०१११८ उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column '२०८१/८२ को यथार्थ खर्च' (रु. लाख) |
| 2082/83 | Rs 0.6 billionरु. ०.६ अर्ब ६१.०६ (रु.करोडमा) वार्षिक विनियोजन | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'आ.व. २०८२/८३ को वार्षिक प्रगति | वार्षिक विनियोजन (रु.करोडमा)' |
| 2082/83 | Rs 0.6 billionरु. ०.६ अर्ब ६०.४७ (रु.करोडमा) वार्षिक बजेट खर्च | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'आ.व. २०८२/८३ को वार्षिक प्रगति | वार्षिक बजेट खर्च (रु.करोडमा)' |
| 2082/83 | Rs 2.9 billionरु. २.९ अर्ब २,९२,३२ रु. लाख | Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84, PDF p.395 (printed p.३७३), budget head row '३३७०१११८ उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column '२०८२/८३ को संशोधित अनुमान' (रु. लाख) |
| 2082/83 | Rs 2.3 billionरु. २.३ अर्ब कोशी कोरिडोरको खाँदबारी-दोभानखण्ड र कालीगण्डकी कोरिडोरको स्तरोन्नति गर्न रु. २ अर्ब ३३ करोड विनियोजन गरेको छु। | Ministry of Financeअर्थ मन्त्रालय बजेट वक्तव्य २०८२/८३ PDF p.60 (printed p.५८), para २५८ |
| 2083/84 | Rs 6.3 billionरु. ६.३ अर्ब ६,२५,०७ रु. लाख | Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84, PDF p.395 (printed p.३७३), budget head row '३३७०१११८ उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column '२०८३/८४ जम्मा बजेट' (रु. लाख) |
| 2083/84 | Rs 6.3 billionरु. ६.३ अर्ब कर्णाली कोरिडोरको ३१ किलोमिटर कालोपत्रे एवम् ग्राभेल गर्नेछौं। त्यस्तै, कालीगण्डकी कोरिडोरको २१ किलोमिटर कालोपत्रे हुनेछ। कोशी कोरिडोरको उत्तरीखण्डको १५ किलोमिटर कालोपत्रे गर्नेछौं। यी तीनवटा कोरिडोरका लागि रु. ६ अर्ब २५ करोड विनियोजन गरेको छु। | Ministry of Financeअर्थ मन्त्रालय बजेट वक्तव्य २०८३/८४ PDF p.19 (printed p.१७), para ४०(ञ) |
Progress over time
Every official progress figure we have found, oldest first. Physical progress is the share of construction work done; financial progress is the share of the budget spent.
| As of | Measure | Figure | Source |
|---|---|---|---|
| २०८१।८२ सम्म (to FY 2081/82) | Physical progress | 45%४५% | Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.50, table row ७ |
| from project start to FY 2081/82आयोजना शुरु भएदेखि आ.व. २०८१/८२ सम्म | Physical progress | 45%४५% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'भौतिक प्रगति (%)' |
| २०८१।८२ सम्म (to FY 2081/82) | Financial progress | 41.25%४१.२५% | Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.3 |
| from project start to FY 2081/82आयोजना शुरु भएदेखि आ.व. २०८१/८२ सम्म | Financial progress | 41.25%४१.२५% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'वित्तीय प्रगति (%)' |
| from project start to FY 2082/83आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म | Physical progress | 49%४९% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'भौतिक प्रगति (%)' |
| from project start to FY 2082/83आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म | Financial progress | 44.98%४४.९८% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'वित्तीय प्रगति (%)' |
Who builds it and who pays?
- Built by
- Department of Roads budget head ३३७०१११८ 'उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)' (as of 2083/84) Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84 PDF p.395
- Ministry
- “भौतिक पूर्वाधार तथा यातायात मन्त्रालय” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.346, para 14 table row ४
- Where
- “मोरङको रानीदेखि संखुवासभाको किमाथाङ्कासम्मको ३४५ किलोमिटरमध्ये संखुवासभाको खाँदबारीदेखि किमाथाङ्कासम्मको १६२ किलोमिटर सडक निर्माण एवं स्तरोन्नति र २३ पुल निर्माण गर्न” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347 (printed p.३१५), para 14.3
- Funding
- २०८३/८४ जम्मा बजेट ६,२५,०७ = नेपाल सरकार ५२,६२ + वैदेशिक ऋण ५,७२,४५ (रु. लाख) - तीनै कोरिडोरको साझा बजेट शीर्षक; ऋण स्रोतमा ए डि बि/ रेज(२१०१०१४), ए डि बि/ रब्लु एस जी आर(२१०१०१५), रेज/ वर्ड बैंक(२१०३०१९), क्याडपिओ / वर्ड बैंक(२१०३०२०), आई एम एफ / ई सि एफ(२१०४००३)(बजेट सहायता) (as of 2083/84) Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84 PDF p.395 (printed p.३७३) head row; capital lines PDF p.396 (printed p.३७४)
What did the Auditor General find?
- Started 2065/66 at Rs 11.93 arba with completion expected 2079/80; cost revised to Rs 16.20 arba and completion now targeted for 2085/86; physical 45%, financial 41.25%. (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.3
- Across the ministry's 6 pride projects: lack of policy/legal arrangements, weak preparation, resource management, inter-agency coordination and stakeholder cooperation mean progress is not satisfactory; projects not completed on time and costs rising. (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd Annual Report 2083, PDF p.347 (printed p.३१५)
Why is it a national pride project?
- “उत्तर दक्षिण (कोशी) सडक योजना” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १४, column 'राष्ट्रिय गौरवका आयोजना नाम'
What could we not establish?
- Original cost differs (1,193 crore NPC progress/OAG vs 1,254.90 crore NPC overrun brief).
- Bridges: 23 (MTEF, OAG scope) vs 24 (OAG progress sentence).
- Budget allocations are for a combined three-corridor head; no corridor-level split in Red Book.
- No project website found/opened.
Last checked 2026-10-17 · Next scheduled check 2026-11-17. We check these figures every month and whenever the Economic Survey, the budget or the Auditor General’s annual report is published. A newer figure is added beside the older ones, so the history stays visible.
How we know this
- National Planning Commissionराष्ट्रिय योजना आयोग: राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण (आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) — source for the facts on this page Checked 2026-10-17
- National Planning Commissionराष्ट्रिय योजना आयोग: राष्ट्रिय गौरवका आयोजनाको समय तथा लागत अधिकता सम्बन्धी संक्षिप्त विवरण (published file dated 2082/06/10; PDF created 2025-10-07) - landing page https://npc.gov.np/content/6731/a-brief-description-of-the-time-and/ — source for the facts on this page Checked 2026-10-17
- National Planning Commissionराष्ट्रिय योजना आयोग: मध्यमकालीन खर्च संरचना (आ.व. २०८३/८४-२०८५/८६) - landing page https://npc.gov.np/content/6803/medium-term-expenditure-structure--fy-2083-84--2085-86-/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: आर्थिक सर्वेक्षण २०८२/८३ (Nepali, authentic) - landing page https://mof.gov.np/content/1738/economic-survey-2082-83/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: आर्थिक सर्वेक्षण २०८१/८२ - landing page https://mof.gov.np/content/1520/economic-survey-2081-82/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: बजेट वक्तव्य आ.व. २०८३/८४ - landing page https://mof.gov.np/content/1741/budget8384/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: बजेट वक्तव्य आ.व. २०८२/८३ - landing page https://mof.gov.np/content/1523/budget-speech-2082-83/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: व्यय अनुमानको विवरण (रातो किताब) आ.व. २०८३/८४ - landing page https://mof.gov.np/content/1745/statement-of-expenditure-estimates--red-book-2083-84/ ; amounts in रु. लाख — source for the facts on this page Checked 2026-10-17
- Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय: महालेखापरीक्षकको त्रिसट्ठिऔँ (६३औं) वार्षिक प्रतिवेदन, २०८३ (published 2026-05-18 / २०८३-०२-०४ per oag.gov.np API) — source for the facts on this page Checked 2026-10-17
Policy Nepal publishes only what official records state. We do not invent or estimate facts; where a record is missing or unclear, we say so. Listings last compiled 2026-10-17. Our approach