North–South Karnali Corridorउत्तर दक्षिण कर्णाली कोरिडोर
Under constructionनिर्माणाधीन Roadsसडक
Facts are shown in the language of the official source they come from. Each figure gives the date it describes.
What is it?
- “कर्णाली कोरिडोर (२६९ किलोमिटर)” (as of 2082/83) Ministry of Financeअर्थ मन्त्रालय Economic Survey 2082/83 (Nepali), PDF p.186, para १०.९
When will it be finished?
- Started
- “२०६९/७०” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'आयोजना शुरु आ.व.'
- First planned completion
- “२०७९।८० मा सम्पन्न गर्ने प्रारम्भिक लक्ष्य रहेकोमा” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.4
Other official figures: “-” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row १३ (original completion not given) - Revised completion
- “२०८४।८५ सम्म अवधि थप भएको देखिन्छ।” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.4
- Revised completion
- “२०८४/८५” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row १३
- Official statement on completion
- “२०६५/६६ - २०८५/८६” (as of MTEF 2083/84) National Planning Commissionराष्ट्रिय योजना आयोग MTEF PDF p.302 (printed p.२९५), budget head ३३७०१११८, column 'आयोजना अवधि (सुरु समाप्ति)'
- Revised completion
- “२०८९/९०” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'आयोजना सम्पन्न हुने आ.व.'
What does it cost?
- First cost estimate
- Rs 18.7 billionरु. १८.७ अर्ब · “१८६६.१९ (रु.करोडमा)” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'आयोजना लागत अनुमान (रु.करोडमा) | शुरु लागत अनुमान'
Other official figures: “आयोजनाको सुरु लागत रु.४ अर्ब १० करोड रहेकोमा” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.4; “४१०.००” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row १३ - Revised cost estimate
- Rs 18.7 billionरु. १८.७ अर्ब · “संशोधनपश्चात् रु.१८ अर्ब ६६ करोड कायम भएको छ।” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.4
- Revised cost estimate
- Rs 6.7 billionरु. ६.७ अर्ब · “६६६.१९” (as of undated brief (its published file name carries 2082/06/10; PDF created 2025-10-07)) National Planning Commissionराष्ट्रिय योजना आयोग NPC overrun brief PDF p.4, Table २, row १३
- Revised cost estimate
- Rs 74.9 billionरु. ७४.९ अर्ब · “७४८६००” (as of MTEF 2083/84) National Planning Commissionराष्ट्रिय योजना आयोग MTEF PDF p.302 (printed p.२९५), budget head ३३७०१११८ 'उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column 'लागत (रु लाखमा)'
- Revised cost estimate
- Rs 29 billionरु. २९ अर्ब · “२९०० (रु.करोडमा)” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'आयोजना लागत अनुमान (रु.करोडमा) | संशोधित लागत अनुमान'
- Spent so far
- Rs 3.3 billionरु. ३.३ अर्ब · “यो वर्ष रु.७७ करोड १५ लाखसमेत हालसम्म रु.३ अर्ब २९ करोड खर्च भई” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.4
- Spent so far
- Rs 2.9 billionरु. २.९ अर्ब · “२८७.०२ (रु.करोडमा)” (from project start to FY 2081/82मिति आयोजना शुरु भएदेखि आ.व. २०८१/८२ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'कुल खर्च (रु.करोडमा)'
- Spent so far
- Rs 3.4 billionरु. ३.४ अर्ब · “३३६.८३ (रु.करोडमा)” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'कुल खर्च (रु.करोडमा)'
Budget each year
| Fiscal year | Figure | Source |
|---|---|---|
| 2081/82 | Rs 5.2 billionरु. ५.२ अर्ब ५,२१,६३ रु. लाख | Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84, PDF p.395 (printed p.३७३), budget head row '३३७०१११८ उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column '२०८१/८२ को यथार्थ खर्च' (रु. लाख) |
| 2082/83 | Rs 1 billionरु. १ अर्ब ९७.०३२ (रु.करोडमा) वार्षिक विनियोजन | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'आ.व. २०८२/८३ को वार्षिक प्रगति | वार्षिक विनियोजन (रु.करोडमा)' |
| 2082/83 | Rs 0.6 billionरु. ०.६ अर्ब ६१.४६ (रु.करोडमा) वार्षिक बजेट खर्च | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'आ.व. २०८२/८३ को वार्षिक प्रगति | वार्षिक बजेट खर्च (रु.करोडमा)' |
| 2082/83 | Rs 2.9 billionरु. २.९ अर्ब २,९२,३२ रु. लाख | Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84, PDF p.395 (printed p.३७३), budget head row '३३७०१११८ उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column '२०८२/८३ को संशोधित अनुमान' (रु. लाख) |
| 2082/83 | Rs 1.3 billionरु. १.३ अर्ब कर्णाली कोरिडोरको लागि रु १ अर्ब २७ करोड बजेट व्यवस्था गरेको छु। | Ministry of Financeअर्थ मन्त्रालय बजेट वक्तव्य २०८२/८३ PDF p.60 (printed p.५८), para २५७ (continued) |
| 2083/84 | Rs 6.3 billionरु. ६.३ अर्ब ६,२५,०७ रु. लाख | Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84, PDF p.395 (printed p.३७३), budget head row '३३७०१११८ उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)', column '२०८३/८४ जम्मा बजेट' (रु. लाख) |
| 2083/84 | Rs 6.3 billionरु. ६.३ अर्ब कर्णाली कोरिडोरको ३१ किलोमिटर कालोपत्रे एवम् ग्राभेल गर्नेछौं। त्यस्तै, कालीगण्डकी कोरिडोरको २१ किलोमिटर कालोपत्रे हुनेछ। कोशी कोरिडोरको उत्तरीखण्डको १५ किलोमिटर कालोपत्रे गर्नेछौं। यी तीनवटा कोरिडोरका लागि रु. ६ अर्ब २५ करोड विनियोजन गरेको छु। | Ministry of Financeअर्थ मन्त्रालय बजेट वक्तव्य २०८३/८४ PDF p.19 (printed p.१७), para ४०(ञ) |
Progress over time
Every official progress figure we have found, oldest first. Physical progress is the share of construction work done; financial progress is the share of the budget spent.
| As of | Measure | Figure | Source |
|---|---|---|---|
| २०८१।८२ सम्म (to FY 2081/82) | Physical progress | 20.75%२०.७५% | Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.50, table row ६; also PDF p.346 table row ५ |
| from project start to FY 2081/82आयोजना शुरु भएदेखि आ.व. २०८१/८२ सम्म | Physical progress | 12%१२% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'भौतिक प्रगति (%)' |
| २०८१।८२ सम्म (to FY 2081/82) | Financial progress | 17.63%१७.६३% | Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.4 |
| from project start to FY 2081/82आयोजना शुरु भएदेखि आ.व. २०८१/८२ सम्म | Financial progress | 9.9%९.९% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'वित्तीय प्रगति (%)' |
| from project start to FY 2082/83आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म | Physical progress | 13%१३% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'भौतिक प्रगति (%)' |
| from project start to FY 2082/83आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म | Financial progress | 11.61%११.६१% | National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'वित्तीय प्रगति (%)' |
Who builds it and who pays?
- Built by
- Department of Roads budget head ३३७०१११८ 'उत्तर दक्षिण राजमार्ग(कर्णाली, कालीगण्डकी र कोशी)' (as of 2083/84) Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84 PDF p.395
- Ministry
- “भौतिक पूर्वाधार तथा यातायात मन्त्रालय” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.346, para 14 table row ५
- Where
- “कर्णाली राजमार्गअन्तर्गत कालीकोटको खुलालुदेखि हुम्लाको सिमिकोट हुँदै हिल्सासम्मको २६९ किलोमिटर सडक” (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347 (printed p.३१५), para 14.4
- Funding
- २०८३/८४ जम्मा बजेट ६,२५,०७ = नेपाल सरकार ५२,६२ + वैदेशिक ऋण ५,७२,४५ (रु. लाख) - तीनै कोरिडोरको साझा बजेट शीर्षक; ऋण स्रोतमा ए डि बि/ रेज(२१०१०१४), ए डि बि/ रब्लु एस जी आर(२१०१०१५), रेज/ वर्ड बैंक(२१०३०१९), क्याडपिओ / वर्ड बैंक(२१०३०२०), आई एम एफ / ई सि एफ(२१०४००३)(बजेट सहायता) (as of 2083/84) Ministry of Financeअर्थ मन्त्रालय Red Book 2083/84 PDF p.395 (printed p.३७३) head row; capital lines PDF p.396 (printed p.३७४)
What did the Auditor General find?
- Started 2069/70 with initial target 2079/80, extended to 2084/85; cost revised from Rs 4.10 arba to Rs 18.66 arba; 268.8 km track, 73 of 216 km gravelled, 3 of 25 bridges built; Rs 3.29 arba spent, financial progress 17.63%. (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd report PDF p.347, para 14.4
- Across the ministry's 6 pride projects: lack of policy/legal arrangements, weak preparation, resource management, inter-agency coordination and stakeholder cooperation mean progress is not satisfactory; projects not completed on time and costs rising. (as of २०८१।८२ सम्म (to FY 2081/82)) Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय OAG 63rd Annual Report 2083, PDF p.347 (printed p.३१५)
Why is it a national pride project?
- “उत्तर दक्षिण कर्णाली कोरिडोर” (from project start to FY 2082/83मिति आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) National Planning Commissionराष्ट्रिय योजना आयोग राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण, PDF p.1, (क) row १६, column 'राष्ट्रिय गौरवका आयोजना नाम'
What could we not establish?
- Start year conflicts (2069/70 vs 2065/66).
- Cost conflicts: original 410 vs 1,866.19 crore; revised 666.19 / 1,866 / 2,900 crore.
- Completion: 2084/85 (OAG, NPC brief) vs 2089/90 (NPC progress statement).
- Gravel km differ: ES 41.5 km, MTEF 32 km, OAG 73 km.
- No project website found/opened.
Last checked 2026-10-17 · Next scheduled check 2026-11-17. We check these figures every month and whenever the Economic Survey, the budget or the Auditor General’s annual report is published. A newer figure is added beside the older ones, so the history stays visible.
How we know this
- National Planning Commissionराष्ट्रिय योजना आयोग: राष्ट्रिय गौरवका आयोजनाको समष्टिगत प्रगति विवरण (आयोजना शुरु भएदेखि आ.व.२०८२/८३ सम्म) — source for the facts on this page Checked 2026-10-17
- National Planning Commissionराष्ट्रिय योजना आयोग: राष्ट्रिय गौरवका आयोजनाको समय तथा लागत अधिकता सम्बन्धी संक्षिप्त विवरण (published file dated 2082/06/10; PDF created 2025-10-07) - landing page https://npc.gov.np/content/6731/a-brief-description-of-the-time-and/ — source for the facts on this page Checked 2026-10-17
- National Planning Commissionराष्ट्रिय योजना आयोग: मध्यमकालीन खर्च संरचना (आ.व. २०८३/८४-२०८५/८६) - landing page https://npc.gov.np/content/6803/medium-term-expenditure-structure--fy-2083-84--2085-86-/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: आर्थिक सर्वेक्षण २०८२/८३ (Nepali, authentic) - landing page https://mof.gov.np/content/1738/economic-survey-2082-83/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: आर्थिक सर्वेक्षण २०८१/८२ - landing page https://mof.gov.np/content/1520/economic-survey-2081-82/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: बजेट वक्तव्य आ.व. २०८३/८४ - landing page https://mof.gov.np/content/1741/budget8384/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: बजेट वक्तव्य आ.व. २०८२/८३ - landing page https://mof.gov.np/content/1523/budget-speech-2082-83/ — source for the facts on this page Checked 2026-10-17
- Ministry of Financeअर्थ मन्त्रालय: व्यय अनुमानको विवरण (रातो किताब) आ.व. २०८३/८४ - landing page https://mof.gov.np/content/1745/statement-of-expenditure-estimates--red-book-2083-84/ ; amounts in रु. लाख — source for the facts on this page Checked 2026-10-17
- Office of the Auditor Generalमहालेखा परीक्षकको कार्यालय: महालेखापरीक्षकको त्रिसट्ठिऔँ (६३औं) वार्षिक प्रतिवेदन, २०८३ (published 2026-05-18 / २०८३-०२-०४ per oag.gov.np API) — source for the facts on this page Checked 2026-10-17
Policy Nepal publishes only what official records state. We do not invent or estimate facts; where a record is missing or unclear, we say so. Listings last compiled 2026-10-17. Our approach